– A HISTORY IN PICTURES –
Early Design (VL) – June 1997 |
That blue CAD again (VL) – 2001 |
|
|
Construction – Imperial, Jan 2001 – Jan 2006
First Light – Imperial, 24 Jan 2006
Surface Testing – Imperial, Jan – Aug 2006
Transport to Boulby – 02/03 Dec 2006
Transport to JIF lab –
Underground Commissioning – Jan 2007
ZEPLIN-III in place – Jan 2007
Approval by STFC – 2 April 2007
Funding for ZEPLIN-III underground
deployment and operation
is approved by the UK
Science & Technology Facilities Council
First Dark – 16 June 2007
Inside neutron shield – 18 June 2007
Ready to run: gamma shield finalised – 19 Feb 2008
First Science Run –27 Feb 2008 to 20 May 2008
First Science Run results – Dec 2008
Photomultiplier array upgraded at long last – Feb 2010
Veto commissioned around ZEPLIN-III – May 2010
Second Science Run – June 2010 to May 2011
Second Science Run results – October 2011
ZEPLIN-III decommissioned at Boulby – 2 Sep 2011