Project Monitor Form System (Milestones)


Project: CALICE

PMF Number:
Project Manager:
Date of PMF:
News and Comment:
Actions from previous PMF:
E-mail web location of CMS VME documentation to Paul Dauncey, RH, 19-12-2003, SQ to check with Paul, done
Provide support & consultancy for testing as required	IC/SAB	Ongoing
Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing, will follow up when the firmware is in place and the board is drawing full operating current
Provide consultancy for BE/VME FPGA, ST/EF, Ongoing
Make sure Route Cards & Problem Reports up to date, SAB, 19-12-2003, ongoing
Update Project Spec and sign off, RH/PD, 15-12-2003, SQ to check with Paul
Test NIM to LVDS module, SAB, 30-11-2004, will be done if required for testing
Actions for this PMF:

 
Milestone Milestones from Project Management Plan Date due in PMP Status
1 Prototype Design Complete 31 May 2003 on
2 Prototype Fabrication Complete 30 Jun 2003 on
3 Prototype Testing Complete 30 Nov 2003 on
4 Design iteration complete 28 Feb 2004 on
5 Production board fabrication complete 31 Mar 2004 on
6 Production Board Testing complete 31 May 2004 on

(if a date is unknown then please set the Year to 'not known')


Staff Booking Data for this Financial Year
(units are in percentage of staff-month, i.e. 100 = 1 staff-month. Staff Booking predictions are shown in blue.)

Person Cost Code Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total (SM)
Rob Halsall FD31720 10 10 10 0 0 0 10 25 25 25 10 10 1.35
Adam Baird FD31720 70 60 60 60 60 60 80 50 50 25 25 25 6.25
Edward Freeman FD31720 0 0 0 0 0 0 0 25 25 25 25 25 1.25
Totals   0.8 0.7 0.7 0.6 0.6 0.6 0.9 1 1 0.75 0.6 0.6 8.85 SM
(0.74 SY)

Is the Project proceeding on Schedule?Yes No
Is the Project proceeding on Budget?Yes No

If not then please enter Comments and Corrective Actions below: