Project Monitor Form System (Milestones)


Project: CALICE

PMF Number: 23
Project Manager: Rob Halsall
Date of PMF: 9 Jan 2004
Date Submitted: 9 Jan 2004
News and Comment: Dates;

The next Calice electronics meeting is on Monday 12th January at 1pm at RAL in the R25/2.82 Training Room.

Procurement status;

The QDR memories, SCSI connectors - no new information

Test & Firmware status;

No testing progress at RAL this week. Some work has been done on the FE FPGA firmware.

QA documentation status;

Distribution of version 0.2. Project Spec is still outstanding.

Calice has now moved over to the new Web based PMF system.
Actions from previous PMF: E-mail web location of CMS VME documentation to Paul Dauncey, RH, 19-12-2003
Meet with Dave Mercer to discuss Final Firmware development, RH, 19-12-2003
Provide support & consultancy for testing as required, IC/SAB, 19-12-2003
Investigate & provide support for power sequencing issues, JS, 19-12-2003
Provide consultancy for BE/VME FPGA, ST/EF, 19-12-2003
Confirm QDR Delivery, SAB, 19-12-2003
Make sure Route Cards & Problem Reports up to date, SAB, 19-12-2003
Order 128MB Compact Flash cards 11 Off, RH, 19-12-2003
Investigate VFE availability & Test Plans, SAB/PD, 19-12-2003
Update Project Spec and sign off, RH/PD, 15-12-2003

Actions for this PMF: E-mail web location of CMS VME documentation to Paul Dauncey, RH, 19-12-2003
Meet with Dave Mercer to discuss Final Firmware development, RH, 19-12-2003
Provide support & consultancy for testing as required IC/SAB 19-12-2003
Investigate & provide support for power sequencing issues, JS, 19-12-2003
Provide consultancy for BE/VME FPGA, ST/EF, 19-12-2003
Confirm QDR Delivery, SAB, 19-12-2003
Make sure Route Cards & Problem Reports up to date, SAB, 19-12-2003
Order 128MB Compact Flash cards 11 Off, RH, 19-12-2003
Investigate VFE availability & Test Plans, SAB/PD, 19-12-2003
Update Project Spec and sign off, RH/PD, 15-12-2003
New Chipscope License for Lab PC, RH, 12-01-2004



Milestone Milestones from Project Management Plan Date due in PMP Status
1 Prototype Design Complete 31 May 2003 Completed on 4 Aug 2003
2 Prototype Fabrication Complete 30 Jun 2003 Completed on 27 Nov 2003
3 Prototype Testing Complete 30 Nov 2003 Predicted on 31 Mar 2004
4 Design iteration complete 28 Feb 2004 Predicted on 29 Apr 2004
5 Production board fabrication complete 31 Mar 2004 Predicted on 31 May 2004
6 Production Board Testing complete 31 May 2004 Predicted on 30 Jul 2004


Staff Booking Data for this Financial Year (when this PMF was created)
(units are in percentage of staff-month, i.e. 100 = 1 staff-month. Staff Booking predictions are shown in blue.)

Person Cost Code AprMayJunJulAugSep OctNovDecJanFebMar Total (SM)
Rob Halsall FD31720 10 10 10 0 0 0 0 0 0 0 0 0 0.3
Adam Baird FD31720 70 60 60 60 60 60 60 60 60 60 60 60 7.3
Totals   0.8 0.7 0.7 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 7.6 SM
(0.63 SY)

Is the Project proceeding on Schedule? y
Is the Project proceeding on Budget? y

Comments and Corrective Actions: