Project Monitor Form System (Milestones)


Project: CALICE

PMF Number: 32
Project Manager: Rob Halsall
Date of PMF: 2 Apr 2004
Date Submitted: 2 Apr 2004
News and Comment: Paul Dauncey has collected 001 from RAL
Adam is not likely to be available to travel over to Paris
The milestones will be reviewed when the Paris tests are complete
Actions from previous PMF: Provide support & consultancy for testing as required IC/SAB Ongoing
Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - minor changes in timing required to reduce current spikes
Provide consultancy for BE/VME FPGA, ST/EF, done
Make sure Route Cards & Problem Reports up to date, SAB,done, all PRs completed
Update Project Spec and sign off, RH/PD, 15-12-2003, SQ and PD need to meet
Actions for this PMF: Provide support & consultancy for testing as required IC/SAB Ongoing
Investigate & provide support for power sequencing issues, JS, 19-12-2003, ongoing - minor changes in timing required to reduce current spikes
Update Project Spec and sign off, RH/PD, 15-12-2003, RH and PD need to meet



Milestone Milestones from Project Management Plan Date due in PMP Status
1 Prototype Design Complete 31 May 2003 Completed on 4 Aug 2003
2 Prototype Fabrication Complete 30 Jun 2003 Completed on 27 Nov 2003
3 Prototype Testing Complete 30 Nov 2003 Predicted on 31 Mar 2004
4 Design iteration complete 28 Feb 2004 Predicted on 29 Apr 2004
5 Production board fabrication complete 31 Mar 2004 Predicted on 31 May 2004
6 Production Board Testing complete 31 May 2004 Predicted on 30 Jul 2004


Staff Booking Data for this Financial Year (when this PMF was created)
(units are in percentage of staff-month, i.e. 100 = 1 staff-month. Staff Booking predictions are shown in blue.)

Person Cost Code AprMayJunJulAugSep OctNovDecJanFebMar Total (SM)
Totals   0 0 0 0 0 0 0 0 0 0 0 0 0 SM
(0.00 SY)

Is the Project proceeding on Schedule? y
Is the Project proceeding on Budget? y

Comments and Corrective Actions: