Project Monitor Form System (Milestones)


Project: CALICE

PMF Number: 39
Project Manager: Rob Halsall
Date of PMF: 21 May 2004
Date Submitted: 21 May 2004
News and Comment: Rob Halsall met with Paul Dauncey on 18-05-2004 to discuss Spec & plans for 2004-2005.

Paul Dauncey took CERC-001 and associated equipment on 18-05-2004 for tests in Paris

Next Meeting is a phone meeting via Rob Halsall's Office on 26-05-2004
Actions from previous PMF: Make correct version of schemtaics & layout available, SAB, 21-05-2004
Get problem reports ready for review, SAB, 28-05-2004
Investigate ADC & DAC ranges, SAB, 28-05-2004
Investigate Power sequencing & configuration problems, SAB, 28-05-2004
Investigate reducing the NIM2LVDS module latency, SAB, 28-05-2004
Write User Guide for CERC in word/pdf format, SAB, 28-05-2004
Order new USB2 Compact Flash programmer on Calice budget, SAB, 21-05-2004
Borrow 3 or 4 SCSI cables for Paris Tests, SAB, 21-05-2004
SAB to investigate noise problems in Paris, SAB, End May
Update Project Specs & Plans for 2004/5 and sign off, RH/PD, 26-05-2003
Actions for this PMF: Make correct version of schemtaics & layout available, SAB, 21-05-2004
Get problem reports ready for review, SAB, 28-05-2004
Investigate ADC & DAC ranges, SAB, 28-05-2004
Investigate Power sequencing & configuration problems, SAB, 28-05-2004
Investigate reducing the NIM2LVDS module latency, SAB, 28-05-2004
Write User Guide for CERC in word/pdf format, SAB, 28-05-2004
Order new USB2 Compact Flash programmer on Calice budget, SAB, 21-05-2004
Borrow 3 or 4 SCSI cables for Paris Tests, SAB, 21-05-2004
SAB to investigate noise problems in Paris, SAB, End May
Update Project Specs & Plans for 2004/5 and sign off, RH/PD, 26-05-2003



Milestone Milestones from Project Management Plan Date due in PMP Status
1 Prototype Design Complete 31 May 2003 Completed on 4 Aug 2003
2 Prototype Fabrication Complete 30 Jun 2003 Completed on 27 Nov 2003
3 Prototype Testing Complete 30 Nov 2003 Predicted on 31 May 2004
4 Design iteration complete 28 Feb 2004 Predicted on 29 Jun 2004
5 Production board fabrication complete 31 Mar 2004 Predicted on 31 Aug 2004
6 Production Board Testing complete 31 May 2004 Predicted on 30 Sep 2004


Staff Booking Data for this Financial Year (when this PMF was created)
(units are in percentage of staff-month, i.e. 100 = 1 staff-month. Staff Booking predictions are shown in blue.)

Person Cost Code AprMayJunJulAugSep OctNovDecJanFebMar Total (SM)
Totals   0 0 0 0 0 0 0 0 0 0 0 0 0 SM
(0.00 SY)

Is the Project proceeding on Schedule? n
Is the Project proceeding on Budget? n

Comments and Corrective Actions:
Project Spec will be updated shortly to reflect new schedule & budget for 2004-2005